 A Polynomial-Time Algorithm for Three-Machine Unit-Job Scheduling
 A patient high-school study guide
 
-How to read this file. This is a study guide to one research paper: the proof that scheduling unit-length precedence-constrained jobs on three identical machines has a polynomial-time exact algorithm. The technical name of the problem is P3 | prec, p_j = 1 | Cmax. The paper is "A Polynomial-Time Algorithm for Three-Machine Unit-Job Scheduling", by OpenAI, dated 24 September 2026. Everything below is written for a patient high-school reader. Each block starts with "Exercise:", then a short question, then a self-contained answer. The Proof paragraphs can be skipped on a first pass and returned to later. Three foundational structural lemmas - (Separator Description), (Any Ideal), and (Shared Cutoffs) - are stated and used freely but not re-proved here; their proofs appear in the original paper's "separators" section. Every other lemma, including the boundary and description lemmas, is proved in full. Named results carry a short nickname in parentheses, e.g. "Lemma (Suffix Carry)"; search for the nickname to find the full statement. Symbols you will meet first: n (number of jobs); x <~ y (x must finish before y, "x precedes y"); DAG (directed acyclic graph); T (candidate deadline); Cmax (makespan, the finish time of the last job); Fam (family of describable sets); K (leaf bound on a description); F (a member of Fam, a Boolean formula); Q(K) (the qualifier set of a list K); lambda(x) (rank of x in a fixed linear extension); D_a, P_a (predecessor and successor cones of slot a); ^D_a, ^P_a (their weak closures).
 
-Parts of this guide. Part A sets up the problem, the notation, and the "shape" of the proof (separators, cones, ranks, normalised sides). Part B is the structural theorem: every feasible schedule can be split at triple boundaries in a bounded-description way. Part C is the algorithm: dynamic programming over the bounded-description family. Part D is the step count. Parts E, F, G discuss assumptions, open problems, and how to read the original paper. Part H is a small Python prototype; Part I collects references.
 
 Exercise: The scheduling problem. What is P3 | prec, p_j = 1 | Cmax?
 The problem is: given n nonpreemptive jobs, each taking exactly 1 unit of time, and a DAG G = (V, E) of "u must finish before v starts" constraints, schedule them on 3 identical parallel machines minimizing the makespan (the finish time of the last job). Equivalently, decide for a given integer T whether all jobs can be scheduled in T slots, each slot running at most 3 jobs, respecting every precedence constraint. The standard shorthand is P3 | prec, p_j = 1 | Cmax, from the Graham-Lawler-Lenstra-Rinnooy-Kan notation. Nothing else is constrained: no release dates, no machine-specific jobs, no extra resources. All units are integer and identical.